Chapter 14, problems 14.1
You have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You forecast 200 attendees. Assume that there is no inventory on hand of any of the items. Explode the bill of material. (Subscripts indicate the number of units required.)

Chapter 14, problems 14.3
The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.
a) Construct a product structure. Identify all levels, parents, and components.
Ans: PRODUCT STRUCTURE FOR PRODUCT S
LEVEL (0)

LEVEL (1)

LEVEL (2)
Chapter 14, problems 14.9
As the production planner for Gerry Cook Products, Inc., you have been given a bill of material for a bracket that is made up of a base, two springs, and four clamps. The base is assembled from one clamp and two housings. Each clamp has one handle and one casting. Each housing has two bearings and one shaft. There is no inventory on hand.
Your boss at Gerry Cook Products, Inc., has just provided you with the schedule and lead times for the bracket in Problem 14.8. The unit is to be prepared in week 10. The lead times for the components are bracket (1 week), base (1 week), spring (1 week), clamp (1 week), housing (2 weeks), handle (1 week), casting (3 weeks), bearing (1 week), and shaft (1 week). a) Prepare the time-phased product structure for the bracket. b) In what week do you need to start the castings?

Chapter 14, problems 14.13
Electro Fans has just received an order for one thousand 20-inch fans due week 7. Each fan consists of a housing assembly, two grills, a fan assembly, and an electrical unit. The housing assembly consists of a frame, two supports, and a handle. The fan assembly consists of a hub and five blades. The electrical unit consists of a motor, a switch, and a knob. The following table gives lead times, on-hand inventory, and scheduled receipts.

a) Construct a product structure.
b) Construct a time-phased product structure.

c) Prepare a net material requirements plan

For getting the instant digital download solution, Please click on the “PURCHASE” link below to get BSOP-330-Master Planning_Week_6_Lab_Assignments_A+ Correct answer

For instant digital download of the above solution or tutorial, please click on the below link and make an instant purchase. You will be guided to the PAYPAL Standard payment page wherein you can pay and you will receive an email immediately with a download link.

In case you find any problem in getting the download link or downloading the tutorial, please send us an email on mail@genietutorial.com